Kit arrival

The empennage arrived on Thursday, February 26. Pretty quick shipping from Vans — the kit tracker estimated it would ship on 2/12 and I got the ABF Freight pickup email on 2/17. Shipping came to $947.

I was expecting a wooden crate like in the various build videos, but Vans now uses a cardboard crate on a wooden pallet for this kit. We opened it up and inventoried the whole thing Thursday night. It didn't take as long as expected, and we were only missing one bag of electrical connectors.

First weekend: vertical stabilizer

On Saturday we jumped right in on the first section: the vertical stabilizer. I cut, drilled, and fit everything together while Shelby deburred. We made a couple of small learning mistakes on the first few pieces and may replace them — still debating. Some of our initial deburring was too aggressive on the rudder mounts (we've already refined that technique), and we accidentally nicked a long piece of metal when deburring it into a different grinding wheel. That other wheel has since been removed.

Overall our confidence grew as we worked through the vertical stabilizer and I think it's turning out pretty good. Between Saturday and Sunday we both put in around 11 hours each. We ended the weekend with all of the vertical stabilizer parts primed and curing for assembly. I also fit and drilled the rudder pieces, which are currently cleco'd in place. Next step is getting those ready for priming too.

Priming notes

Priming went okay. Not enough paint was coming out of the gun, even with the flow completely open. It's going to take some fine-tuning, but I'm sure we'll figure it out.

Photos

The crate — cardboard now, not wood. Lift-gate service included.
The crate — cardboard now, not wood. Lift-gate service included.

Opened up for inventory night.
Opened up for inventory night.

Inventoried all over the office.
Inventoried all over the office.

Then moved to shelves in the workshop.
Then moved to shelves in the workshop.

Working on the vertical stabilizer.
Working on the vertical stabilizer.

The rudder cleco'd together.
The rudder cleco'd together.

Vertical stabilizer pieces primed.
Vertical stabilizer pieces primed.

Ribs and spars after priming.
Ribs and spars after priming.

Skins — one primed, one not yet.
Skins — one primed, one not yet.

The mistake piece: the flange side of the lower spar cap.
The mistake piece: the flange side of the lower spar cap.