Tailcone priming & riveting
Another 23 hours combined this weekend (8 for me, 15 for Shelby). She almost lapped me in hours with all the deburring. Deburring, cleaning, etching, priming
Cross-cutting tag. Entries here can live in different folders.
Another 23 hours combined this weekend (8 for me, 15 for Shelby). She almost lapped me in hours with all the deburring. Deburring, cleaning, etching, priming
We've made a lot more progress. It doesn't look like much because we're priming everything, but it's one more bite of the elephant. Our process
It's been a while since an update. Between the basement remodel, family visiting, and flight lessons, the build took a back seat for a few weeks. We're back in full swing now. Another 6.5 hours for me, 8 hours for Shelb…
Kit arrival The empennage arrived on Thursday, February 26. Pretty quick shipping from Vans — the kit tracker estimated it would ship on 2/12 and I got the ABF Freight pickup email on 2/17. Shipping came to $947.
Here's the first post for our RV-12iS #121708 build log. We're going the E-LSA route, so we don't technically need a build log, but it's a good record to look back on — and a place to collect opinions we can either list…